  "tool": "tlctc-control-work-planner",
  "schemaVersion": 1,
  "programme": {
    "name": "Control uplift 2027",
    "sponsor": "CISO",
    "manager": "PMO lead",
    "startDate": "2026-11-01",
    "endDate": "2027-06-30",
    "statusNote": "Detection work on plan; patch SLA waits for the asset inventory.",
    "targetMaturity": 3
  },
  "environments": [
    { "id": "env-prod", "name": "Production" },
    { "id": "env-corp", "name": "Corporate IT" }
  ],
  "milestones": [
    { "id": "ms-soc", "name": "SOC detection baseline", "date": "2027-01-31", "description": "Central detection covers the internal clusters #1 to #7." }
  ],
  "items": [
    {
      "id": "edr-prod",
      "title": "EDR rollout to production servers: detection and host isolation",
      "type": "local",
      "envId": "env-prod",
      "cells": ["7-DE", "7-RS"],
      "cellDone": { "7-DE": "2026-11-10" },
      "control": "EDR",
      "owner": "Server team",
      "status": "in-progress",
      "priority": "P1",
      "startDate": "2026-10-15",
      "dueDate": "2026-12-15",
      "effortEst": 15,
      "milestoneId": "ms-soc",
      "maturityFrom": 1,
      "maturityTo": 3,
      "checklist": [
        { "text": "Linux servers", "done": true },
        { "text": "Windows servers", "done": false }
      ]
    },
    {
      "id": "siem",
      "title": "Central SIEM: correlation for clusters #1 to #7",
      "type": "umbrella",
      "scope": "all",
      "cells": ["1-DE", "2-DE", "3-DE", "4-DE", "5-DE", "6-DE", "7-DE"],
      "control": "Central SIEM",
      "owner": "SOC lead",
      "status": "planned",
      "priority": "P1",
      "dueDate": "2027-01-31",
      "effortEst": 60,
      "dependsOn": ["edr-prod"],
      "milestoneId": "ms-soc",
      "updates": [
        { "date": "2026-11-12", "text": "Licence renewal in procurement." }
      ]
    }
  ],
  "raid": [
    {
      "kind": "risk",
      "title": "SIEM licence renewal not yet approved",
      "severity": "high",
      "status": "open",
      "owner": "Programme manager",
      "dueDate": "2026-11-30",
      "itemIds": ["siem"],
      "mitigation": "Business case with three volume scenarios."
    }
  ]
}